Week 9, Day 57 - Roof On & Sliding Doors In

This week saw the roof go from a frame to fully completed in a matter of 3 or 4 days.

It's amazing how different a colour can look when it's viewed as a whole piece rather than a tiny colour-chip.  I think it looks a lot lighter than the samples - this is not such a bad thing :) but it seems to look different as the light changes.  We are so pleased that we've gone with the tin roof, a nice clean look and hopefully one that will keep the possums out!

The sliding doors in the rumpus room and dining room were also installed this week, so we've been testing out the "breeze-factor" having them wide open after all this hot weather we've been having.

We were a little surprised to see that the plumber had been this week to run the pipes throughout the house, and that the plaster and cornices had been delivered along with the external doors.

We met the guy who will be installing the hebel panels on Friday afternoon.  He said they are due to start towards the end of next week, and going well, it should only take around 4 days to complete.

I guess it won't be too long until it's at lock-up stage!














Dining Room sliding door
leads out to the extra driveway 
Rumpus Room sliding door
we hope to eventually have this lead out to a deck or paved area