We have a start date!!!

Well, today I had a call from PD with the all important site start date that we have been so eager to get.


This is all obviously dependant on the weather, but here are the dates we've been given;

  • Site Cut – 7/12/11
  • Retaining Wall – 8/12/11
  • Set Out – 9/12/11
  • Piers – 12/12/11
  • Drains – 13/12/11
  • Underground Power – 13/12/11
  • Slab Start – 14/12/11
  • Slab Pour – 16/12/11
This certainly makes it all feel very real now!

Friday, 25 November 2011

Sign off

Yesterday we had an appointment with PD to check all the PCVs and Final Drawings.  All was great, the bank is happy, PD are happy and we are happy!

Lisa has informed us that we will be given a site start date next week some time, with the view of having the slab down and possibly the frame done before Christmas.